布里斯托爾95年來的第一個新火車站被推遲建造

3週前
布里斯托爾95年來的第一個新火車站被推遲建造

布里斯托爾近100年來的第一個新火車站的開放被進一步推遲了。

英格蘭西部聯合管理局(WECA)證實,塞文海灘線上的Portway Park and Ride車站要到 "明年初 "才會準備就緒。

到目前為止,該站已耗資420萬英鎊,本應在夏季開放。

WECA的一位發言人說,延誤的原因是為車站安裝電力供應和數據電纜。

波特威站將是自1927年帕森街以來,布里斯托爾第一個開通的車站。

WECA告訴BBC西區,一些延誤是由於在建設階段 "採購基本部件的準備時間較長",而在裝修過程中,進一步的延誤也影響了現場。

該局補充說:"所有各方都在努力工作,以儘快解決這些問題,但安全驗證過程是複雜的,是由一個獨立的機構完成的,並在強制性的時間範圍內工作。


The opening of the first new railway station in Bristol for almost 100 years has been further delayed.

Portway Park and Ride station on the Severn Beach line won't be ready until "early next year", the West of England Combined Authority (WECA) confirmed.

The station, which has so far cost £4.2m, should have opened in the summer.

A WECA spokesperson said delays were around fitting the station out with electrical supply and data cabling.

Portway station will be the first to open in Bristol since Parson Street in 1927.

WECA told BBC West some of the delays have come as a result of "longer lead in times for the procurement of essential components" during the building phase, and further delays have hit the site during the fitting out process.

The authority added: "All parties are working hard to resolve these issues as quickly as possible, but the safety validation process is complex and is completed by an independent body, working to mandatory timescales.